HDD work completed on Seagreen onshore cabling package

05/10/2021
HDD works at the A90 near Tealing, Angus

CONTRACTORS on what will be Scotland’s largest offshore windfarm have reached a project milestone with the completion of Horizontal Directional Drilling (HDD) works. This work package was a key part of the project and now provides the ability to install the electrical cables required to transmit the electricity generated from the windfarm.

HDD is a technique that is used for the installation of ducting and avoids the need for open trenching/excavation. This has been used to insert ducting at eight locations along the onshore cabling route between landfall at the coast of Carnoustie and the project’s new substation currently under construction at Tealing airfield. 

Locations where HDD has been used include a number of A Roads including the major A90 and A92 trunk roads, water course crossings, a Site of Specific Scientific Interest (Barry Links SSSI) and even the main East Coast rail line which connects Aberdeen to London. 

Onshore Project Manager for Seagreen, Steven Reid said:

“We’re very pleased with the delivery of the HDD works by the project team and our Contractors, where the works have been completed safely and with a minimum amount of disturbance.

“The non-intrusive nature of Horizontal Directional Drilling means that it has a minimal environmental impact. It reduces noise, vibration, waste and earthworks in comparison to the traditional method of open trenching, where plant machinery is used for the bulk removal and reinstatement of earthworks. In addition, the installation process has enabled key local and national transportation routes to remain open throughout and resulted in no disruption to route users whilst the works took place below ground.

“We would like to place our thanks to the people of Angus for their continued patience whilst these works were undertaken and also to the various Stakeholders that supported during the design and construction phases. The project team will now continue to work with our Principal Contractor Nexans to safely deliver the final construction works required for the installation of the electrical infrastructure.”

Steps in the HDD process:

  • The HDD installation depths for cable route range from 4m to 13m.
  • A launch and receive pit are constructed and using GPS coordinates and a pilot drill is then commenced to follow the designed alignment.
  • Extension drill rods are added to the drill bit as it progresses though the soils below the surface. A surveying system, which guides the rotating drill rods along the required alignment, is located behind the drill bit.
  • Once the pilot hole exits at the receiving pit, a larger diameter drill called a Reamer is then pulled back through the path of the pilot hole towards the launch pit.
  • The process is repeated until the correct borehole size has been achieved using increased Reamer sizes.
  • During the drilling process, a material called bentonite (a natural clay) is injected through the borehole to lubricate and cool the drill bit and stabilise the pilot hole. The bentonite also mixes with the excavated material and carries it back to the launch pit.
  • Once the drilling process is complete and the required size of borehole has been achieved the cable ducts are then pulled through the open borehole. The ends are then capped to prevent any unplanned material or wildlife entering the ducts until such times the ducts (installed by HDD) are connected to the ducts being installed by the traditional open cut method.

Works are currently underway in Angus to pull electrical cabling through 19.5 kilometres of underground ducts which will connect the £3 billion Seagreen Wind Farm to the Scottish national grid. The cable installation work is scheduled to be completed by Spring 2022.

When complete, Seagreen – a joint venture between TotalEnergies and SSE Renewables – will be Scotland’s single largest source of renewable energy, providing enough renewable energy to power 1.6 million homes.

The Latest Stories

Boost in small business hiring offset by slow sales growth as Scotland and the North lead the way 
GRAHAM named on £600M Scottish Framework
Wood Appoints New Director
RAW Capital Partners appoints new Chief Marketing Officer