- Shetland Space Centre Limited, which operates SaxaVord Spaceport, reported a 2025 loss before tax of £7.56m, up from £5.40m in 2024.
- Revenue rose to £3.19m from £2.54m. The group’s operating loss was £5.31m, against £4.60m the year before.
- The group completed a capital raise on 27 October 2026, including a £30m equity investment by the UK Government, and says it is now debt free.
- Two launch service providers are working towards a launch before the end of 2026, according to the directors.
Full Article
Shetland Space Centre Limited, the company behind SaxaVord Spaceport in Unst, reported a loss before tax of £7.56m for 2025, compared with £5.40m in 2024.
The group’s consolidated accounts for the year ended 31 December 2025 show revenue of £3.19m, up from £2.54m. The group’s operating loss was £5.31m, compared with £4.60m. Finance costs rose to £2.27m from £0.88m.
The directors’ strategic report says the operating loss was in line with the group’s business plan and reflected planned growth in activity and staff costs as it prepares for launch operations. It describes the group as being in an operating loss-making position “as is expected at this stage of its build phase”.
Cash outflow on capital expenditure during 2025 was £9.3m, bringing total property, plant and equipment to £49.5m. The report says all infrastructure needed to support the first test launch was completed during the year, and that the group now operates a fully functioning mission management centre, tracking and telemetry system and flight termination system. Work continues on hangar integration facilities and cleanrooms, which are required to support clients launching with payloads from 2027. Cash and cash equivalents were £0.9m at both the 2025 and 2024 year ends.
After the year end, on 27 October 2026, the group completed a transformational capital raise. It comprised a £30m equity investment by the UK Government and a contracted commitment from a major shareholder to provide up to a further £30m, of which £2.5m has been received and converted into equity. Loan notes and accrued interest totalling £33.6m were also converted into equity. The group says it is now debt free.
The directors say the funding is forecast to cover the cost of completing three fully operational launchpads and the period of anticipated monthly losses until launch cadence delivers the profitability in the business plan. The group remains in negotiation with several launch providers over contracts for launchpads two and three.
On launches, the directors say that two launch service providers are working towards a launch before the end of 2026. The report states: “The directors are confident that these will be the first of many launches from SaxaVord Spaceport.”
In Case You Missed It:
Scottish National Investment Bank reports £138m net loss as five early-portfolio failures land in one year
SaxaVord lines up £60m public-private package to unlock UK orbital launches from Shetland
Scottish Rugby cuts annual loss to £1.4m as revenue rises
Calnex reports orders up more than 20% as first-half revenue rises 5%
The report also notes that the group depends on the success of its customers and their launch vehicles, and that uncertainty remains over the timing of the group’s full benefit from the developing market.
Johnston Carmichael LLP, the group’s auditor, gave an unmodified opinion on the accounts and reported that it had not identified material uncertainties that may cast significant doubt on the group’s ability to continue as a going concern for at least twelve months from when the statements are authorised for issue.